Gujarat · Buyer's rights · Reviewed 29 Sep 2026

Gujarat RERA complaint against a builder (2026)

What you can complain about, how to file on GujRERA 2.0, what the Authority can order, how interest is computed, and how appeals and enforcement work.

Updated

Quick answer

Any allottee can file a complaint online on GujRERA 2.0 against a registered promoter or agent; the main remedies are a refund with interest, monthly interest for delay, compensation and orders to perform. Hearings are listed on the portal and can be attended online; appeals go to the Gujarat Real Estate Appellate Tribunal within 60 days.

Get the current price sheet

Before you file: three checks

  • The date. Delay is measured from the completion date in the RERA certificate (and any extension), not the handover date the sales team quoted. Decode it in our RERA check guide.
  • Your own compliance. Section 19 obliges you to pay instalments on time; a promoter will raise your defaults in defence.
  • A written demand. Send a notice by email and registered post stating the breach and the relief you want. The reply, or silence, goes into your complaint.

Grounds and remedies under the Act

Common complaints to Gujarat RERA and the remedy for each
ProblemSectionWhat you can ask for
Possession delayed beyond the RERA date18Refund with interest, or interest every month until possession; compensation
Promoter will not refund after you withdraw18, 19Refund with interest within the time the Authority fixes
More than 10% taken before a registered agreement13Direction to execute and register the agreement; penalty on promoter
Plan or specification changed without consent14Restoration or compensation; two-thirds allottee consent required for changes
Defects within 5 years of possession14(3)Rectification within 30 days or compensation
Carpet area delivered is less than agreed14, 18Proportionate refund with interest
Society not formed or common areas not conveyed11(4), 17Direction to form the association and execute conveyance
Misleading advertisement or unregistered sale3, 12Refund with interest and compensation; penalties on promoter

How to file on GujRERA 2.0, step by step

  1. Go to gujrera.gujarat.gov.in and register as a Citizen with your mobile number and email.
  2. Open Complaint → File Complaint. Choose whether the respondent is a promoter or an agent, and select the registered project.
  3. Choose the forum: the Authority for directions, interest and refund; the Adjudicating Officer if you are claiming compensation for loss under sections 12, 14, 18 or 19.
  4. Write the facts in order with dates, cite the sections, and state the exact relief: amount, interest, direction.
  5. Upload the agreement, receipts, brochure, correspondence and photographs as PDFs.
  6. Pay the fee online and submit; note the complaint number.
  7. Watch the Hearing List on the home page for your date; hearings are held through the e-court module and you may appear in person or online, with or without an advocate.
  8. After the order, download it under Judgement/Order. If the promoter does not comply, apply for execution; RERA orders are recoverable as arrears of land revenue.

The Authority publishes a user manual for grievance redressal on the portal's Website Guide; read it before filing because field names change between portal versions.

Interest on delay: how it is computed

Gujarat's rules set the interest payable by promoter or allottee at the State Bank of India's highest marginal cost of funds based lending rate (MCLR) plus 2%, as simple interest. It runs from the date the money was paid until it is refunded, or for each month of delay beyond the declared completion date if you keep the home. The same rate applies both ways, so the Authority will also compute interest on any instalments you paid late.

After the order: appeal and enforcement

Either side may appeal to the Gujarat Real Estate Appellate Tribunal within 60 days (section 44). A promoter's appeal is entertained only after depositing at least 30% of the penalty, or the full amount of refund and interest ordered, with the Tribunal. From the Tribunal, an appeal lies to the Gujarat High Court within 60 days on a question of law (section 58). If no appeal is filed and the promoter still does not pay, the order is executed as arrears of land revenue through the Collector. Continued non-compliance attracts a daily penalty of up to 5% of the project cost (section 63).

Gujarat RERA's complaint record

On 29 Sep 2026 the GujRERA home page showed 6,337 citizen complaints received under section 31 against 1,537 projects, 4,705 resolved, and 5,718 suo motu actions initiated by the Authority against 3,595 projects with 4,469 orders issued. The Authority sits in Gandhinagar and hears matters through its e-court module.

Alternatives and what not to do

You may go to the District Consumer Commission instead of RERA for deficiency in service, but not to both for the same relief. Criminal complaints for cheating are a separate track and do not get your money back faster. Do not stop paying instalments without an order: section 19 makes you liable for interest, and a promoter can cancel the allotment after notice. Do not sign a one-sided settlement or a fresh agreement with a later date without advice; it resets your section 18 rights.

Related Gujarat guides

Check a project on Gujarat RERA · Ready vs under construction: how your money is protected · Buying process and documents · Carpet area under RERA.

Sources

  1. GujRERA — official portal, complaint module and home page statistics — checked 29 Sep 2026
  2. GujRERA — User manual for RERA 2.0 grievance redressal (complaint) — official
  3. GujRERA — Hearing list (e-court cause list) — official
  4. GujRERA — Acts, rules, regulations and fees — official
  5. Real Estate (Regulation and Development) Act, 2016 — sections 3, 12–14, 18, 19, 31, 44, 58, 63 — official

Last reviewed 29 Sep 2026 by the Surat Niwas research desk under our editorial policy. This guide summarises the Act and GujRERA's published process; it is not legal advice. For a specific dispute consult an advocate practising before the Authority. This guide is general information, not legal, tax or investment advice — confirm figures with the official portal, your bank or your advocate before you act.

Frequently asked questions

How do I file a complaint with Gujarat RERA?

Register as a citizen on gujrera.gujarat.gov.in (GujRERA 2.0), open Complaint → File Complaint, select the registered project and promoter, state the facts and relief sought under the Act, upload your agreement, payment proofs and correspondence, pay the fee online and submit. You receive a complaint number; hearings are listed in the e-court cause list and can be attended online.

What is the fee for a RERA complaint in Gujarat?

A fee of ₹1,000 per complaint is charged on the GujRERA portal at the time of filing, as published in the Authority's fee schedule; confirm the current amount under Acts, Rules, Regulations and Fees before paying.

What can I complain about to RERA?

Possession delayed beyond the RERA-declared date, refusal to refund, demands beyond the agreement, charging for area not delivered, deviation from sanctioned plans, structural or workmanship defects within five years of possession, failure to form the society or convey common areas, false advertising, and taking more than 10% before a registered agreement.

What does RERA do after a complaint against a builder?

The Authority (or an adjudicating officer for compensation claims) issues notice to the promoter, holds hearings, and passes an order: refund with interest, interest for delay, compensation, a direction to perform, or penalties on the promoter. Orders are enforceable like a civil court decree and are published on the portal.

What compensation is payable for possession delay in Gujarat?

Under section 18 you may withdraw and claim the full amount paid with interest, or stay and receive interest for every month of delay until possession. Gujarat's rules peg the interest to the State Bank of India's highest marginal cost of lending rate plus 2%. Separate compensation for loss can be claimed before the adjudicating officer.

How do I check Gujarat RERA complaint status?

Log in to GujRERA 2.0 and open Complaint → View Complaint for the stage, next hearing and orders. Hearing dates for all matters are also published in the public Hearing List (cause list) on the home page, and final orders appear under Judgement/Order.

How long does a RERA complaint take in Gujarat?

The Act asks the Authority to dispose of complaints within 60 days where practicable. In practice matters take a few hearings over several months; uncontested refund claims move fastest, defect and plan-deviation disputes slowest.

Can I complain to RERA about an unregistered project?

Yes. Selling or advertising an unregistered project is itself a violation of section 3, and the Authority acts suo motu as well as on complaints. You can also complain about a registered agent or an unregistered intermediary.

Can I appeal a Gujarat RERA order?

Yes, to the Gujarat Real Estate Appellate Tribunal within 60 days of the order (section 44); a promoter appealing must first deposit at least 30% of the penalty or the amount ordered. A further appeal lies to the Gujarat High Court on a question of law within 60 days (section 58).

RERA or consumer forum: which is better?

You may choose either, not both for the same relief. RERA is specialist, usually faster and its orders include statutory interest; the consumer commission can award broader compensation for deficiency in service. Most delayed-possession buyers in Gujarat go to RERA first.

Can a group of buyers file one complaint?

Each allottee files on their own agreement, but buyers from one project commonly file together with identical facts and the Authority hears them as a batch. An association of allottees can also complain about common-area and conveyance issues.

What documents do I need for a RERA complaint?

The agreement for sale or allotment letter, every payment receipt and bank statement, the brochure and advertisements relied on, the RERA certificate and declared completion date, all written demands and replies, photographs of defects or site status, and your ID. Upload them as PDFs when filing.